"Applicant" means the developer, owner, or operator who submits an application to the department for a permit by rule pursuant to this chapter.
"Archaeological field survey" means systematic identification-level archaeological investigations as described in DHR's guidelines for conducting historic resources survey within the project area and submission of necessary documentation to DHR with recommendations on eligibility of identified resources for listing in the Virginia Landmarks Register and National Register of Historic Places.
"Architectural field survey" means comprehensive, reconnaissance-level documentation as described in DHR's guidelines for conducting historic resources survey of all standing buildings or structures 50 years of age or older within the project area and surrounding areas with a view to the project and submission of necessary documentation to DHR with recommendations on eligibility of identified resources for listing in the Virginia Landmarks Register and National Register of Historic Places.
"아카이브 검색" 은 DHR의 문화자원 목록에서 이전에 기록된 고고학적 유적지의 존재 여부와 건축 구조물 및 지구를 검색하는 것을 의미합니다.
"Begin commercial operation" means to have begun to generate electricity for sale, excluding the sale of test generation.
"Begin construction" means a continuous program of construction or land-disturbing activity necessary to construct a small solar energy project.
"해안 조류 보호 구역" 또는 "CAPZ" 는 부서의 해안 GEMS 지리공간 데이터 시스템(9VAC15-60-120 C 1)에서 생성된 "해안 조류 보호 구역" 의 지도에 지정된 지역을 의미합니다.
"Complete application" means an application the department has determined meets the requirements of this chapter.
"집광형 태양광 발전" 또는 "CPV" 는 태양광 셀에 태양광을 집중하거나 방향을 조정하는 장치를 갖춘 태양광 발전 시스템을 의미합니다. 이 장의 목적상, CPV는 PV의 정의에 포함됩니다.
"DACS" 는 미국 농무부 소비자 서비스국을 의미합니다.
"부서" 는 환경품질부, 그 책임자 또는 책임자의 지명자를 의미합니다.
"DCR" 은 보존 및 레크리에이션 부서를 의미합니다.
"DCR Virginia Solar Site Pollinator/Bird Habitat Scorecard" or "DCR Scorecard" means assessment tool used to establish target conditions for pollinator friendly habitat.
"DGIF" 는 게임 및 내륙 어업부를 의미합니다.
"DHR" 은 역사 자원부를 의미합니다.
"Disturbance zone" means the area within the site directly impacted by land-disturbing activity, including construction and operation of the small solar energy project and within and 100 feet of from the boundary of the directly impacted area. For purposes of the DCR Virginia Solar Site Pollinator/Bird Habitat Scorecard, the disturbance zone shall include the panel zones, open areas, and screening zones of the project.
"Document certification" means the following statement signed by the responsible official or person and submitted to the department with the application documents for a permit by rule. This certification also applies to all supplemental information provided to the department after the initial application submittal:
"I certify under penalty of law that this document and all attachments were prepared under my direction or supervision in accordance with a system designed to assure that qualified personnel properly gather and evaluate the information submitted. Based on my inquiry of the person or persons who manage the system, or those persons directly responsible for gathering and evaluating the information, the information submitted is, to the best of my knowledge and belief, true, accurate, and complete. I am aware that there may be significant penalties for submitting false information, including the possibility of fine and imprisonment for knowing violations."
"DWR" 은 야생동물 자원부를 의미합니다.
"역사적 자원(" )이란 버지니아 주법 § 10 에 따라 버지니아 주 역사적 유적 등록부(Virginia Landmarks Register)에 포함되거나 포함될 자격을 갖춘 모든 선사 시대 또는 역사적 지역, 유적지, 건물, 구조물, 물체 또는 문화적 경관을 의미합니다. 버지니아 주법 §1-2205 및 버지니아 주 행정규칙(VAC) 175-30-40 부터 17까지의 규정에 따라 적용됩니다.5-30-70.
"통합형 태양광 발전(" )은 지붕재와 같은 건축 자재에 태양광 발전 시스템을 통합한 것을 의미합니다.
"연결점" 는 태양광 발전 프로젝트가 전력망으로 전력을 전송하기 위해 변전소와 연결되는 지점 또는 지점들을 의미합니다.
"Land disturbance" or "land-disturbing activity" means a manmade change to the land surface that potentially changes its runoff characteristics, including clearing, grading, or excavation, except that the term shall not include those exemptions specified in § 62.1-44.15:34 of the Code of Virginia.
"메가와트" 또는 "MW" 는 전력 측정을 의미하며, 1,000 킬로와트는 1MW에 해당합니다.
"자연유산 자원(" )이란 희귀, 멸종 위기 또는 멸종 위기에 처한 동식물 종의 서식지, 희귀하거나 국가적으로 중요한 자연 군락 또는 지질학적 유적지, 연방 시민의 복지에 도움이 되는 과학적 관심의 대상이 되는 유사한 지형지물을 의미합니다.
"의향서 통지" 또는 "NOI" 는 이 장에 따라 허가를 위한 서류를 제출하겠다는 신청자의 의사를 해당 부서에서 수용 가능한 방식으로 통지하는 것을 의미합니다.
"개방 지역"은 DCR 버지니아 태양광 사이트 수분 매개자/조류 서식지 스코어카드의 목적상 프로젝트 부지 경계 내 패널 구역을 벗어난 모든 지역을 의미합니다.
"운영자(" )는 태양광 에너지 프로젝트의 전체 운영 및 관리를 담당하는 사람을 의미합니다.
"기타 태양광 기술" 은 PV(광전변환) 또는 CPV(집광형 태양광 발전) 이외의 태양광으로부터 전기를 생산하는 재료, 장치 또는 방법을 의미합니다.
"Owner" means the person who owns all or, a portion of, or has any property interest in a solar energy project.
"Panel zone" means, for purposes of the DCR Virginia Solar Site Pollinator/Bird Habitat Scorecard, the area underneath the solar arrays, including inter-row spacing of a disturbance zone.
"주차장" 은 일반적으로 자동차 주차를 위해 개별 공간으로 구분되고 포장 또는 자갈로 덮인 개량된 공간을 의미합니다.
"Permit by rule," "PBR," or "permit" means provisions of the regulations stating that a project or activity is deemed to have a permit if it meets the requirements of the provision.
"Person" means any individual, partnership, firm, association, joint venture, public or private corporation, trust, estate, commission, board, public or private institution, utility, cooperative, county, city, town, or other political subdivision of the Commonwealth, any interstate body, or any other legal entity.
" "광전변환(Photovoltaic) 또는 광전변환(" ) PV(" )는 반도체를 통해 태양광을 흡수하고 직접 전기로 변환하는 재료 및 장치를 의미합니다.
" "광전지 셀(Photovoltaic cell) 또는 광전지 셀(", PV 셀(" )은 태양광을 직접 전기로 변환하는 고체 상태의 장치입니다. PV 셀은 서로 연결되어 PV 모듈을 형성할 수 있으며, 이 모듈들은 다시 결합되고 연결되어 PV 배열(일반적으로 PV 패널이라고도 함)을 형성할 수 있습니다.
"광전변환 시스템(Photovoltaic system)" 또는 "PV 시스템(" )은 PV 셀을 의미하며, 이는 하나 이상의 PV 모듈 또는 배열로 연결될 수 있으며, 관련 배선, 전기 연결부, 설치 하드웨어, 전력 조정 장비(인버터), 및 저장 배터리 등을 포함합니다.
"Preconstruction" means any time prior to commencing land-clearing operations beginning land-disturbing activities necessary for the installation of energy-generating structures at the small solar energy project.
"Previously disturbed or repurposed areas" means the land area within the property boundary of industrial or commercial properties, including brownfields, or previously mined areas. It does not include active or fallow agricultural land or silvicultural land-use.
"Rated capacity" means the maximum capacity of a small solar energy project based on Photovoltaic USA Test Conditions (PVUSA Test Conditions) rating, measured in MW.
"담당자" 의미합니다:
1. 법인 또는 유한책임회사의 경우, 주요 업무 기능을 담당하는 사장, 비서, 재무 또는 부사장 또는 법인 또는 유한책임회사를 위해 유사한 정책 또는 의사 결정 기능을 수행하거나 버지니아주 법령 제 13.1 조의 적용을 받는 기타 사람입니다;
2. 파트너십 또는 개인 사업체의 경우 각각 일반 파트너 또는 소유주.
3. 버지니아주 법령( 15.2 )의 적용을 받는 지방 정부 기관 또는 주, 연방 또는 기타 공공 기관의 경우, 최고 경영자 또는 고위 선출직 공무원이 해당됩니다.
"선별 구역"은 DCR 버지니아 태양광 발전소 수분 매개자/조류 서식지 스코어카드의 목적상 식생이 우거진 시각적 장벽을 의미합니다.
"Site" means the area containing of a solar energy project that is under common ownership or operating control. Electrical infrastructure and other appurtenant structures up to the interconnection point shall be considered to be within the site.
"Small renewable energy project" means (i) an electrical generation facility with a rated capacity not exceeding 150 megawatts MW that generates electricity only from sunlight or wind; (ii) an electrical generation facility with a rated capacity not exceeding 100 megawatts MW that generates electricity only from falling water, wave motion, tides, or geothermal power; or (iii) an electrical generation facility with a rated capacity not exceeding 20 megawatts MW that generates electricity only from biomass, energy from waste, or municipal solid waste.
"Small solar energy project," "solar energy project," or "project" means a small renewable energy project that (i) generates electricity from sunlight, consisting of one or more PV systems and other appurtenant structures and facilities within the boundaries of the site; and (ii) is designed for, or capable of, operation at a rated capacity equal to or less than 150 megawatts MW. Two or more solar energy projects otherwise spatially separated but under common ownership or operational control, which are connected to the electrical grid under a single interconnection agreement, shall be considered a single solar energy project. Nothing in this definition shall imply that a permit by rule is required for the construction of test structures to determine the appropriateness of a site for the development of a solar energy project.
"T&E," "state threatened or endangered species," or "state-listed species" means: any wildlife species designated as a Virginia endangered or threatened species by DGIF pursuant to the §§ 29.1-563 through 29.1-570 of the Code of Virginia and 4VAC15-20-130.
"Virginia Pollinator Protection Strategy" means a statewide strategy pursuant to § 3.2-108.1 of the Code of Virginia.
"버지니아 자연 경관 평가 생태 코어(" )는 DCR에서 식별한 자연 및 비자연 토지 피복 사이의 가장 가까운 가장자리에서 안쪽으로 100 미터부터 시작하여 최소 100 연속 에이커의 내부 면적을 가진 대규모 자연 토지를 의미합니다.
"VLR"은 버지니아 Virginia 랜드마크 등록부 (9 VAC15-60-120 B 1)를 의미합니다.
"VLR 대상 역사적 자원(" )이란 버지니아 역사적 자원 위원회( 17)의 역사적 자원 목록(5)에 따라 VLR에 등재되기 위한 기준을 충족하지만, VLR에 등재되지 않은 역사적 자원을 의미합니다. 해당 기준은 버지니아 행정 규정(VAC)의 다음과 같은 규정에 따라 적용됩니다: -30-40 부터 17VAC5-30-70
"VLR 등재" 는 17VAC5-30-40 를 통해 17VAC5-30-70 의 기준에 따라 VLR에 등재된 기록 자료를 의미합니다.
"야생동물" 은 야생동물을 의미하지만, 곤충 종은 자연유산 자원의 일부로만 다루어지며 야생동물로 간주되지 않습니다(단, T&E 곤충 종은 T&E 야생동물로 간주되지 않습니다).
A. This regulation is issued under authority of Article 5 (§ 10.1-1197.5 et seq.) of Chapter 11.1 of Title 10.1 of the Code of Virginia. The regulation contains requirements for solar-powered electric generation projects consisting of PV systems and associated facilities with a single interconnection to the electrical grid that are designed for, or capable of, operation at a rated capacity equal to or less than 150 megawatts. This chapter applies throughout the Commonwealth of Virginia. Nothing in this chapter shall be interpreted to affect the rights of a private property owner. 
B. 해당 부서는 정격 용량이 5메가와트 초과이고 방해 구역이 10 에이커 초과인 소규모 태양광 에너지 프로젝트에 대해 규칙에 따른 허가가 필요하다고 결정했습니다. 단, 해당 프로젝트가 본 장의 제3부(9VAC15-60-130)의 기준을 충족하지 않는 경우에 한하며, 본 규정은 이러한 프로젝트에 대한 규칙에 따른 허가 규정을 본 장의 제2부(9VAC15-60-30 등)에 포함하고 있습니다.
C. The department has determined that different provisions should apply to projects that meet the criteria as set forth in Part III (9VAC15-60-130) of this chapter, and this regulation contains the requirements, if any, for these projects in Part III (9VAC15-60-130 A, B, and B) C) of this chapter. Projects that meet the criteria for Part III of this chapter are deemed to be covered by the permit by rule.
D. The department has determined that small renewable energy projects utilizing other solar technologies shall fulfill all of the requirements in 9VAC15-40 as prescribed for small wind energy projects, unless (i) the owner or operator of the proposed project presents to the department information indicating that the other solar technology presents no greater likelihood of significant adverse impacts to natural resources than does PV technology and (ii) the department determines that it is appropriate for the proposed project utilizing the other solar technology to meet the requirements of this chapter or of some modification to either 9VAC15-40 or this chapter, as prescribed by the department for that particular project.
A. The owner or operator of The application for a small solar energy project with a rated capacity greater than five megawatts and a disturbance zone greater than 10 acres, provided that the project does not otherwise meet the criteria for Part III (9VAC15-60-130 A, B, and B) C) of this chapter, shall submit to the department a complete application in which he satisfactorily accomplishes contain all of the following:
1. In accordance with § 10.1-1197.6 B 1 of the Code of Virginia, and as early in the project development process as practicable, furnishes to the department a notice of intent, to be published in the Virginia Register, that he intends to submit the necessary documentation for a permit by rule for a small renewable energy project; A NOI to submit the necessary documentation for a permit by rule, to be published in the Virginia Register.
a. The applicant shall submit the NOI in a form approved by the department along with the appropriate fee pursuant to 9VAC15-60-110.
(1) 초기 NOI는 가능한 한 프로젝트 개발 프로세스 초기에 해당 부서에 제출하되, 9VAC15-60-90 에 따라 요구되는 공개 의견 수렴 기간이 시작되기 최소 90 일 전에 제출해야 합니다.
(2) The NOI shall be submitted to the chief administrative officer and chief elected official of the locality in which the project is proposed to be located the same time the notice is submitted to the department.
b. The NOI shall expire if no application has been submitted within 48 months from the NOI submittal date unless the department receives a written request for extension prior to the NOI expiration date.
(1) A NOI extension may be granted for an additional 36 months at which time the NOI shall expire.
(2) A new NOI and appropriate fee shall be required for any project to be permitted under the PBR for which a NOI has expired.
c. An applicant seeking changes for a project that results in an increase of MW or acreage shall submit a new NOI using the appropriate form. No additional fee shall be assessed.
d. NOI change of operator, ownership, or controlling interest for a project shall require a notification to the department within 30 days of the transfer. No additional fee shall be assessed.
(1) 최초 신청자는 해당 부서에서 허용하는 양식으로 최초 NOI를 철회하여 변경 사항을 해당 부서에 통지해야 합니다.
(2) 신규 신청자는 해당 부서에서 허용하는 양식으로 NOI를 제출해야 합니다.
(3) The department shall not consider the change of operator, ownership, or controlling interest for a project effective until the department receives notification from both the original applicant and the new applicant.
2. In accordance with § 10.1-1197.6 B 2 of the Code of Virginia, furnishes to the department a A certification by the governing body of the locality or localities wherein the small renewable energy project will be located that the project complies with all applicable land use ordinances;.
3. In accordance with § 10.1-1197.6 B 3 of the Code of Virginia, furnishes to the department copies Copies of all interconnection studies undertaken by the regional transmission organization or transmission owner, or both, on behalf of the small renewable energy project;.
4. In accordance with § 10.1-1197.6 B 4 of the Code of Virginia, furnishes to the department a A copy of the final interconnection agreement between the small renewable energy project and the regional transmission organization or transmission owner indicating that the connection of the small renewable energy project will not cause a reliability problem for the system.
a. If the final agreement is not available, the most recent interconnection study shall be sufficient for the purposes of this section.
When a final interconnection agreement is complete, it b. The final agreement shall be provided to the department within 30 days of the date of execution.
c. The department shall forward a copy of the agreement or study to the State Corporation Commission;.
5. In accordance with § 10.1-1197.6 B 5 of the Code of Virginia, furnishes to the department a A certification signed and stamped by a professional engineer licensed in Virginia that the maximum generation capacity of the small solar energy project, as designed, does not exceed 150 megawatts; MW.
6. In accordance with § 10.1-1197.6 B 6 of the Code of Virginia, furnishes to the department an An analysis of potential environmental impacts of the small renewable energy project's operations on attainment of national ambient air quality standards;.
7. In accordance with § 10.1-1197.6 B 7 of the Code of Virginia, furnishes to the department, where relevant, an An analysis of the beneficial and adverse impacts of the proposed project on natural resources. The owner or operator shall perform the analyses prescribed in pursuant to 9VAC15-60-40 or 9VAC15-60-45, as applicable. For wildlife, that analysis shall be based on information on the presence, activity, and migratory behavior of wildlife to be collected at the site for a period of time dictated by the site conditions and biology of the wildlife being studied, not exceeding 12 months;.
8. In accordance with § 10.1-1197.6 B 8 of the Code of Virginia, furnishes to the department a A mitigation plan pursuant to 9VAC15-60-60 that details reasonable actions to be taken by the owner or operator to avoid, minimize, or otherwise mitigate such impacts, and to measure the efficacy of those actions; provided, however, that the provisions of this subdivision shall only be required if the department determines, pursuant to 9VAC15-60-50, that the information collected pursuant to § 10.1-1197.6 B 7 of the Code of Virginia and 9VAC15-60-40 indicates that significant adverse impacts to wildlife or historic resources are likely. The mitigation plan shall be an addendum to the operating plan of the solar energy project, and the owner or operator shall implement the mitigation plan as deemed complete and adequate by the department. The mitigation plan shall be an enforceable part of the permit by rule; or 9VAC15-60-65, as applicable, if a determination of likely significant adverse impacts has been made according to 9VAC15-60-50 or 9VAC15-60-55, as applicable.
The plan shall detail actions necessary to avoid, minimize, or otherwise mitigate such impacts, and to measure the efficacy of those actions.
9. 에  따라 §.10 11197-.6 B 9 버지니아주 법령 에 따라  프로젝트가 9VAC15-60- 에 따라 설계되었다는 버지니아주에서 면허를 취득한 전문 엔지니어가 서명하고 날인한 A 인증서를.80
10. In accordance with § 10.1-1197.6 B 10 of the Code of Virginia, furnishes to the department an An operating plan that includes a description of how the project will be operated in compliance with its mitigation plan, if such a mitigation plan is required pursuant to 9VAC15-60-50; and any mitigation plan required due to findings under 9VAC15-60-50 or 9VAC15-60-55, as applicable.
11. In accordance with § 10.1-1197.6 B 11 of the Code of Virginia, furnishes to the department a A detailed site plan meeting the requirements of 9VAC15-60-70;.
12. In accordance with § 10.1-1197.6 B 12 of the Code of Virginia, furnishes to the department a A certification signed by the applicant that the small solar energy project has registered or applied for or obtained all necessary environmental permits;.
13. In accordance with § 10.1-1197.6 H and I of the Code of Virginia, furnishes to the department a A certification signed by the applicant that the small solar energy project is being proposed, developed, constructed, or purchased by a person that is not a utility regulated pursuant to Title 56 of the Code of Virginia or provides certification that (i) the project's costs are not recovered from Virginia jurisdictional customers under base rates, a fuel factor charge, or a rate adjustment clause, or (ii) the applicant is a utility aggregation cooperative formed under Article 2 (§ 56-231.38 et seq.) of Chapter 9.1 of Title 56 of the Code of Virginia;.
14. Prior to authorization of the project and in accordance with § 10.1-1197.6 B 13 and B 14 of the Code of Virginia, conducts a A summary report of the 30-day public review and comment period and holds a public meeting conducted pursuant to 9VAC15-60-90. The public meeting shall be held in the locality or, if the project is located in more than one locality, in a place proximate to the location of the proposed project. Following the public meeting and public comment period, the applicant shall prepare a report summarizing, including a summary of the issues raised by the public and include any written comments received and the applicant's response to those comments. The report shall be provided to the department as part of this application; and
15. In accordance with 9VAC15-60-110, furnishes to the department the The appropriate fee fees pursuant to 9VAC15-60-110.
B. Within 90 days of receiving all of the required documents and fees listed in subsection A of this section, the department shall determine, after consultation with other agencies in the Secretariat of Natural Resources, whether the application is complete and whether it adequately meets the requirements of this chapter pursuant to § 10.1-1197.7 A of the Code of Virginia. An applicant seeking a PBR under this part shall submit the following:
1. 이 섹션의 하위 섹션 A에 명시된 모든 항목은 해당 부서에서 허용하는 형식으로 제출하고 9VAC15-60-110 에 따라 모든 해당 수수료가 부과됩니다.
2. 신청서와 함께 제출하는 자기소개서에는 다음 내용이 포함되어야 합니다:
a. 다음 내용이 포함된 책임자의 서명이 있는 문서 인증:
"I certify under penalty of law that this application document and all attachments were prepared under my direction or supervision in accordance with a system designed to ensure that qualified personnel properly gather and evaluate the information submitted. Based on my inquiry of the person or persons who manage the system, or those persons directly responsible for gathering and evaluating the information, the information submitted is, to the best of my knowledge and belief, true, accurate, and complete. I am aware that there may be significant penalties for submitting false information, including the possibility of fine and imprisonment for knowing violations."
b. 이 하위 섹션 2 a에 따라 요구되는 문서 인증에 서명하는 책임자의 이름 및 연락처 정보.
c. 허가 승인을 받을 담당자의 이름과 연락처 정보입니다.
C. Within 90 days of receiving all of the required documents and fees listed in subsection A of this section, the department shall, after consultation with DCR, DHR, and DWR, form a determination that an application is administratively complete or incomplete.
1. If the department determines that the application meets the requirements of this chapter, then the department shall form a determination that an application is administratively complete and notify the applicant responsible person in writing that he is authorized to construct and operate a small solar energy the project pursuant to this chapter.
a. The authorization to construct and operate shall become invalid if (i) a program of continuous construction or modification is not begun within 60 months from the date the PBR or modification authorization is issued or (ii) a program of construction or modification is discontinued for a period of 24 months or more, except for a department-approved period between phases of a phased construction project.
b. 부서는 사안별로 연장을 허가할 수 있습니다.
c. Any project for which the PBR or modification authorization has been deemed invalid will require a new NOI, application documents and appropriate fees to reactivate authorization.
2. If the department determines that the application does not meet the requirements of this chapter, then the department shall form a determination that an application is administratively incomplete and notify the applicant in writing and specify the deficiencies.
3. If the applicant chooses to correct deficiencies in a previously submitted an incomplete application, (i) the applicant shall notify the department within 30 days of an incomplete notification, (ii) the department shall follow the procedures of this subsection, and (iii) the department shall notify the applicant within 60 days whether the revised application supplemental information meets the requirements of this chapter within 60 days of receiving the revised application.
4. 이 하위 섹션에 따른 부서의 모든 사건 결정은 행정 절차법(§ 2.2-4000 이하 버지니아주 법령)의 절차 및 항소 조항의 적용을 받습니다.
A. Analyses of wildlife. To fulfill the requirements of § 10.1-1197.6 B 7 of the Code of Virginia, the applicant shall conduct preconstruction wildlife analyses. The analyses of wildlife shall include the following: This section applies to all applications submitted prior to (12 months after the effective date of the amendments). For purposes of this section, 9VAC15-60-50, and 9VAC15-60-60, the definition of:
1. "T&E," "state threatened or endangered species," or "state-listed species" means any wildlife species designated as a Virginia endangered or threatened species by DWR pursuant to the §§ 29.1-563 through 29.1-570 of the Code of Virginia and 4VAC15-20-130.
2. "Wildlife" means wild animals; except, however, that T&E insect species shall only be addressed as part of natural heritage resources and shall not be considered T&E wildlife.
B. The applicant shall conduct preconstruction wildlife analyses. The analyses of wildlife shall include the following:
1. Desktop surveys and maps. The applicant shall obtain a wildlife report and map generated from DGIF's DWR's Virginia Fish and Wildlife Information Service web-based application (9VAC15-60-120 C 3) or from a data and mapping system including the most recent data available from DGIF's DWR's subscriber-based Wildlife Environmental Review Map Service of the following: (i) known wildlife species and habitat features on the site or within two miles of the boundary of the site and (ii) known or potential sea turtle nesting beaches located within one-half mile of the disturbance zone.
2. Desktop map for avian resources in Coastal Avian Protection Zones (CAPZ). The applicant shall consult the "Coastal Avian Protection Zones" map generated on the department's Coastal GEMS geospatial data system (9VAC15-60-120 C 1) and determine whether the proposed solar energy project site will be located in part or in whole within one or more CAPZ.
B. Analyses of historic resources. To fulfill the requirements of § 10.1-1197.6 B 7 of the Code of Virginia, the C. The applicant shall also conduct a preconstruction historic resources analysis. The analysis shall be conducted by a qualified professional meeting the professional qualification standards of the Secretary of the Interior's Standards for Archeology and Historic Preservation (9VAC15-60-120 B 2) in the appropriate discipline. The analysis shall include each of the following:
1. 알려진 역사적 자료의 집대성. 신청인은 방해 구역 내 및 방해 구역 경계로부터 반 마일 이내에 위치한 알려진 역사적 자원에 대한 정보를 수집하고, 이 정보를 버지니아 주 건축 및 건축물 부서( 9)의 VAC15-60-70 B에 참조된 맥락 지도에 표시하거나 이 맥락 지도에 중첩하여 표시하며, 동시에 표 형식으로 제출해야 합니다.
2. 건축 조사. 신청인은 방해 구역 내 및 방해 구역 경계로부터 반 마일 이내에 위치한 모든 건축 자원을 대상으로 현장 조사를 실시해야 하며, 이에는 문화 경관, 50 연령 이상의 건축물이 포함됩니다. 또한, 식별된 자원이 VLR에 등재될 자격이 있는지 평가해야 합니다.
3. 고고학 조사. 신청인은 방해 구역에 대한 고고학 현장 조사를 실시하고, 식별된 고고학 유적지의 VLR 등재 적격성을 평가하여야 합니다. 이 고고학 조사를 수행하는 대신, 신청인은 해당 부서에 프로젝트가 비침투형 기초 공법을 사용할 것임을 입증하고, 건설 전 사이트의 필요한 지형 정리가 고고학 유적에 부정적인 영향을 미칠 가능성이 없음을 증명할 수 있습니다.
C. Analyses of other natural resources. To fulfill the requirements of § 10.1-1197.6 B 7 of the Code of Virginia, the D. The applicant shall also conduct a preconstruction desktop survey of natural heritage resources within the disturbance zone.
D. E. Summary report. The applicant shall provide to the department a report presenting the findings of the studies and analyses conducted pursuant to subsections A B, B C, and C D of this section, along with all data and supporting documents. The applicant shall assess and describe the expected beneficial and adverse impacts, if any, of the proposed project on wildlife and historic resources identified by these studies and analyses.
A. This section applies to applications submitted after (12 months after the effective date of the amendments). For purposes of this section, 9VAC15-60-55 and 9VAC15-60-65:
1. The definition of "T&E," "state threatened or endangered species," or "state-listed species" means (i) any wildlife species designated as a Virginia endangered or threatened species by DWR pursuant to the §§ 29.1-563 through 29.1-570 of the Code of Virginia and 4VAC15-20-130 or (ii) any species designated as a Virginia endangered or threatened species by DACS pursuant to § 3.2-1000-1100 of the Code of Virginia and 2VAC5-320-10.
2. The definition of "Wildlife" means wild animals; except, however, that T&E insect species shall be considered T&E wildlife.
B. The applicant shall conduct preconstruction wildlife analyses. The analyses of wildlife shall include the following:
1. A wildlife report and map generated either (i) from DWR's Virginia Fish and Wildlife Information Service web-based application (9VAC15-60-120 C 3) or (ii) from a data and mapping system including the most recent data available from DWR's subscriber-based Wildlife Environmental Review Map Service of the following: (a) known wildlife species and habitat features on the site or within two miles of the boundary of the site, (b) known or potential sea turtle nesting beaches located within one-half mile of the disturbance zone, and (c) desktop information for bald eagle nesting locations from the Center for Conservation Biology at the College of William and Mary.
2. Desktop map for avian resources in Coastal Avian Protection Zones (CAPZ). The applicant shall consult the "Coastal Avian Protection Zones" map generated on the department's Coastal GEMS geospatial data system (9VAC15-60-120 C 1) and determine whether the proposed project site will be located in part or in whole within one or more CAPZ.
3. 신청자는 이러한 연구 및 분석을 통해 확인된 제안된 프로젝트가 야생동물에 미칠 것으로 예상되는 유익한 영향과 부정적인 영향(있는 경우)을 평가하고 설명해야 합니다.
C. The applicant shall perform a preconstruction historic resources analysis conducted by a qualified professional meeting the qualification standards of the Secretary of the Interior's Standards for Archeology and Historic Preservation (9VAC15-60-120 B 2) in the appropriate discipline. Any study or analysis required under this subsection submitted to DHR for review may be considered accepted by DHR if DHR does not provide comments within 30 calendar days from confirmed receipt of an analysis determined to be administratively complete. In this case, the applicant may assume DHR concurrence with the recommendations of the study or analysis and proceed accordingly. The analysis shall include each of the following:
1. 교란 구역 내 및 교란 구역 경계로부터 0.5마일 이내에 있는 알려진 역사적 자원에 대한 정보는 9VAC15-60-70 B에 참조된 상황 지도에서 확인하거나 이 상황 지도에 오버레이된 표 형식과 표로 확인할 수 있습니다.
2. An architectural field survey of all architectural resources, including cultural landscapes 50 years of age or older within the disturbance zone and within one-half mile of the disturbance zone boundary, and an evaluation of the eligibility of any identified resource for listing in the VLR. The architectural survey area may be refined by the applicant based on an analysis to exclude areas that have no direct view to the project. The applicant shall provide detailed justification for any changes to the survey area.
3. An archaeological field survey of the disturbance zone and an evaluation of the eligibility of any identified archaeological site for listing in the VLR. To streamline archaeological investigations, the survey may be guided by a research design that utilizes a probability assessment or predictive modeling. Such a research design shall be approved by DEQ and DHR for use in the project prior to conducting the fieldwork.
D. The applicant shall conduct a preconstruction desktop survey of natural heritage resources and Virginia Natural Lands Assessment Ecological Cores within the disturbance zone within six months prior to the date of the application submittal. The analysis shall include:
1. A report of natural heritage resources using either the DCR online information service order form or the DCR subscriber-based Natural Heritage Data Explorer web application pursuant to 9VAC15-60-120 C 2 and include the most recent data available on the following:
a. Documented occurrences of natural heritage resources within 100 feet of the site;
b. Intersection of the site with predicated suitable habitat (PSH) models developed by DCR for rare, threatened, and endangered species;
c. Intersection of the site with the Virginia Natural Landscape Assessment Ecological Cores; and
d. Onsite surveys for natural heritage resources recommended by DCR based on the analysis required under this subsection.
2. A completed DCR Virginia Solar Site Pollinator/Bird Habitat Scorecard (9VAC15-60-120 B 5).
A. This section applies to applications submitted prior to (12 months after the effective date of the amendments).
B. The department shall find that significant adverse impacts to wildlife are likely whenever the wildlife analyses prescribed in 9VAC15-60-40 A B document that any of the following conditions exists:
1. 국가 지정 멸종위기종인 T&E 야생동물이 교란 구역 내부에 존재하거나, 교란 구역이 알려진 또는 잠재적인 바다거북 산란 해변으로부터 반 마일 이내에 위치해 있습니다.
2. 방해 구역은 해안 조류 보호 구역(CAPZ) 지도상의 다음 구역의 일부 또는 전체에 위치합니다: 1, 2, 3, 4, 5, 10, 11, 12, 또는 14.
비. C. The department shall find that significant adverse impacts to historic resources are likely whenever the historic resources analyses prescribed by 9VAC15-60-40 B C indicate that the proposed project is likely to diminish significantly any aspect of a historic resource's integrity.
A. This section applies to applications submitted after (12 months after the effective date of the amendments).
B. The department shall find that significant adverse impacts to wildlife are likely whenever the wildlife analyses prescribed in 9VAC15-60-45 B document that any of the following conditions exists:
1. State-listed T&E wildlife species are found to occur within the disturbance zone or the disturbance zone is located on or within one-half mile of a known or potential sea turtle nesting beach.
2. 방해 구역은 해안 조류 보호 구역(CAPZ) 지도상의 다음 구역의 일부 또는 전체에 위치합니다: 1, 2, 3, 4, 5, 10, 11, 12, 또는 14.
C. The department shall find that significant adverse impacts to historic resources are likely whenever the historic resources analyses prescribed by 9VAC15-60-45 C indicate that the proposed project is likely to diminish significantly any aspect of a historic resource's integrity.
D. The department shall find that significant adverse impacts to natural heritage resources and ecological cores are likely whenever the analysis prescribed by 9VAC15-60-45 D indicates that natural heritage resources or Virginia Natural Landscape Assessment Ecological Cores with a Conservation Rank of C1 or C2 occur within the disturbance zone.
A. This section applies to applications submitted prior to (12 months after the effective date of the amendments).
B. If the department determines that significant adverse impacts to wildlife or historic resources or both are likely, then the applicant shall prepare a mitigation plan.
비. C. Mitigation measures for significant adverse impacts to wildlife shall include:
1. For state-listed T&E wildlife, the applicant shall take all reasonable measures to avoid significant adverse impacts or shall demonstrate in the mitigation plan what significant adverse impacts cannot practicably be avoided and why additional proposed actions are reasonable. These additional proposed actions may include best practices to avoid, minimize, or offset adverse impacts to resources analyzed pursuant to 9VAC15-60-40 A or C 9VAC15-60-40 B or D.
2. 교란 구역이 알려진 또는 잠재적인 바다거북 산란 해변에서 0.5마일 이내에 위치한 제안 프로젝트의 경우, 신청자는 중대한 악영향을 피하기 위해 모든 합리적인 조치를 취하거나 완화 계획에서 실질적으로 피할 수 없는 중대한 악영향과 추가로 제안된 완화 조치가 합리적인 이유를 입증해야 합니다. 완화 조치에는 다음이 포함되어야 합니다:
a. Avoiding construction within likely sea turtle crawl or nesting habitats during the turtle nesting and hatching season (May 20 through October 31). If avoiding construction during this period is not possible, then conducting daily crawl surveys of the disturbance zone (May 20 through August 31) and one mile beyond the northern and southern reaches of the disturbance zone (hereinafter "sea turtle nest survey zone") between sunrise and 9 a.m. by qualified individuals who have the ability to distinguish accurately between nesting and nonnesting emergences.
b. 산란기에 공사가 예정된 경우 바다거북 둥지 조사 구역 내에서 발견된 둥지와 새끼를 보호하기 위한 조치를 포함해야 합니다.
c. 산란기에는 야간 공사를 최소화하고 공사 및 운영 단계에서는 프로젝트 조명을 설계하여 산란 중인 바다거북과 부화 중인 새끼 거북에 미치는 영향을 최소화합니다.
3. 해안 조류 보호 구역(CAPZ) 지도상의 다음 구역 1, 2, 3, 4, 5, 10, 11, 12 또는 14 에 부분적으로 또는 전체적으로 위치한 프로젝트의 경우, 부서에서 지정하는 기금에 프로젝트의 정격 용량 1메가와트당 $1,000,00 를 기부해야 합니다. 이 기금은 CAPZ 내 프로젝트가 조류 자원에 미치는 영향을 조사하는 과학적 연구를 지원하기 위해 사용됩니다.
C. D. Mitigation measures for significant adverse impacts to historic resources shall include:
1. 태양광 에너지 프로젝트의 설계나 식생 또는 기타 차폐 시설 설치를 통해 VLR 대상 또는 VLR 목록에 등재된 건축 자원에 미치는 중대한 부정적 영향을 가능한 범위 내에서 최소화해야 합니다.
2. VLR 적격 또는 VLR 목록에 등재된 건축 자원에 대한 중대한 부정적 영향을 피하거나 최소화하여 더 이상 중대한 부정적 영향이 발생하지 않도록 할 수 없는 경우, 신청자는 중대한 부정적 영향을 상쇄하고 해당 자원 또는 유사한 자원에 대한 공익과 혜택을 입증할 수 있는 합리적이고 비례적인 완화 계획을 개발해야 합니다.
3. 확인된 VLR 대상 또는 VLR 목록에 등재된 고고학 유적지를 피하거나 중대한 부정적 영향을 피할 수 있을 정도로 최소화할 수 없는 경우, 고고학 데이터 복구를 통해 프로젝트의 중대한 부정적 영향을 완화할 것입니다.
A. This section shall apply to applications submitted after (12 months after the effective date of the amendments).
B. The applicant shall prepare a mitigation plan for any resource for which a significant adverse impact determination has been made as a result of the analysis pursuant to 9VAC15-60-55. The plan shall detail actions by the applicant to avoid, minimize, or otherwise mitigate such impacts and shall be an enforceable part of the PBR.
C. Mitigation measures for significant adverse impacts to wildlife shall include the following:
1. For state-listed T&E wildlife, the applicant shall take all reasonable measures to avoid significant adverse impacts or shall demonstrate in the mitigation plan what significant adverse impacts cannot practicably be avoided and why additional proposed actions are reasonable. These additional proposed actions may include best practices to avoid, minimize, or offset adverse impacts to resources analyzed pursuant to 9VAC15-60-45 B or D.
2. 교란 구역이 알려진 또는 잠재적인 바다거북 산란 해변에서 0.5마일 이내에 위치한 제안 프로젝트의 경우, 신청자는 중대한 악영향을 피하기 위해 모든 합리적인 조치를 취하거나 완화 계획에서 실질적으로 피할 수 없는 중대한 악영향과 추가로 제안된 완화 조치가 합리적인 이유를 입증해야 합니다. 완화 조치에는 다음이 포함되어야 합니다:
a. Avoiding construction within likely sea turtle crawl or nesting habitats during the turtle nesting and hatching season (May 20 through October 31). If avoiding construction during this period is not possible, then conducting daily crawl surveys of the disturbance zone (May 20 through August 31) and one mile beyond the northern and southern reaches of the disturbance zone (sea turtle nest survey zone) between sunrise and 9 a.m. by qualified individuals who have the ability to distinguish accurately between nesting and nonnesting emergences.
b. 산란기에 공사가 예정된 경우 바다거북 둥지 조사 구역 내에서 발견된 둥지와 새끼를 보호하기 위한 조치를 포함해야 합니다.
c. 야간 공사를 피할 수 없는 경우, 공사 및 운영 단계에서 프로젝트 조명을 설계하여 둥지를 틀고 있는 바다거북과 부화하는 새끼에게 미치는 영향을 최소화하세요. 제안된 프로젝트 조명은 공사 전에 DWR과 미국 어류 및 야생동물 관리국에 제출하여 승인을 받아야 합니다.
3. For projects located in part or in whole within zones 1, 2, 3, 4, 5, 10, 11, 12, or 14 on the Coastal Avian Protection Zones (CAPZ) map, contribute $1,000 per MW of rated capacity, or partial MW thereof, to a fund designated by the department in support of scientific research investigating or minimizing the impacts of projects in CAPZ on avian resources. Payment of mitigation fee is due at the time of application submittal.
D. Mitigation measures for significant adverse impacts to historic resources shall include the following:
1. Significant adverse impacts to VLR-eligible or VLR-listed architectural resources shall be minimized to the extent practicable through design of the solar energy project or the installation of vegetative or other screening.
2. VLR 적격 또는 VLR 목록에 등재된 건축 자원에 대한 중대한 부정적 영향을 피하거나 최소화하여 더 이상 중대한 부정적 영향이 발생하지 않도록 할 수 없는 경우, 신청자는 중대한 부정적 영향을 상쇄하고 해당 자원 또는 유사한 자원에 대한 공익과 혜택을 입증할 수 있는 합리적이고 비례적인 완화 계획을 개발해야 합니다.
3. 확인된 VLR 대상 또는 VLR 목록에 등재된 고고학 유적지를 피하거나 중대한 부정적 영향을 피할 수 있을 정도로 최소화할 수 없는 경우, 고고학 데이터 복구를 통해 프로젝트의 중대한 부정적 영향을 완화할 것입니다.
E. Mitigation measures for significant adverse impacts to natural heritage resources described in Virginia Natural Landscape Assessment Ecological Cores shall include all reasonable measures to avoid and minimize significant adverse impacts. The applicant shall demonstrate in a mitigation plan what significant adverse impacts cannot practicably be avoided and why additional proposed actions are reasonable. Additional proposed actions shall include practices to minimize or offset significant adverse impact through activities to protect, restore, or enhance the affected or similar resource.
A. The applicant shall submit a site plan that includes maps showing the physical features, topography, and land cover of the area within the site, both before and after construction of the proposed project. The site plan shall be submitted at a scale sufficient to show, and shall include, the following: (i) the boundaries of the site; disturbance zone with 100 foot buffer, panel zone, open areas, and screening areas; (ii) the location, height, and dimensions of all existing and proposed PV systems, other structures, fencing, and other infrastructure; (iii) the location, grades, and dimensions of all temporary and permanent on-site onsite and access roads from the nearest county or state maintained road; and (iv) water bodies, waterways, wetlands, and drainage channels; and (v) location of any mitigation measures and resources subject to mitigation.
B. 신청자는 사이트가 포함되는 지역과 사이트 경계로부터 5마일 이내의 지역이 포함된 상황도를 제출해야 합니다. 상황 지도에는 주 및 연방 자원 토지 및 기타 보호 지역, 해안 조류 보호 구역, 9VAC 25- 830-80 에 따른 체서피크만 자원 보호 지역, 역사 자원, 주 도로, 수로, 지역 경계, 숲, 열린 공간, 농지, 재개발 부지, 송전 및 변전소 인프라가 표시되어야 합니다.
C. 신청자는 상업 운영을 시작한 후 6개월 이내에 부지 내 지역의 물리적 특징, 지형 및 토지 피복이 표시된 건설 후 부지 지도를 해당 부서에 제출해야 합니다. 지도에는 다음이 포함되어야 합니다:
1. The boundaries of the site, disturbance zone with 100-foot buffer identified, open areas, and screening areas;
2. 패널 배치;
3. Mitigation required pursuant to 9AVC15-60-60 or 9VAC15-60-65, as applicable; and
4. 프로젝트 설계 결과 피할 수 있는 문화 자원의 위치.
A. The design and installation of the small solar energy project shall incorporate any requirements of the mitigation plan that pertain to design and installation if a mitigation plan is required pursuant to 9VAC15-60-50, 9VAC15-60-55, 9VAC15-60-60, or 9VAC15-60-65 as applicable.
B. The applicant shall prepare an operation plan detailing operational parameters for the project including (i) remote monitoring or staffing requirements, (ii) emergency procedures and contacts, (iii) vegetation to be used within the disturbance zone and 100-foot buffer, and (iv) application frequency of herbicides over the life of the project. Owners and operators are encouraged to utilize the link to the DACS Fieldwatch (9VAC15-60-120 B 6) prior to the application of either pesticides or herbicides.
A. Before the initiation of any construction at the small solar energy project, the applicant shall comply with this section. The owner or operator shall first publish a notice once a week for two consecutive weeks in a major local newspaper of general circulation informing the public that he intends to construct and operate a project eligible for a permit by rule. No later than the date of newspaper publication of the initial notice, the owner or operator shall submit to the department a copy of the notice along with electronic copies of all documents that the applicant plans to submit in support of the application. The notice shall include: The applicant shall conduct a public comment period for public review of all application documents required by 9VAC15-60-30 and include a summary report of the public comment as part of the PBR application. The report shall include documentation of the public comment period and public meeting and include a summary of the issues raised by the public, any written comments received, and the applicant's response to those comments.
B. The applicant shall publish a notice announcing a 30-day comment period. The notice shall be published once a week for two consecutive weeks in a local newspaper of general circulation where the project is to be located and in at least one local newspaper that reaches low-income or minority populations in the area where the project is to be located identified by the locality. The notice shall include the following:
1. 제안된 프로젝트의 간략한 설명 및 위치, 포함하여 부지의 대략적인 크기, 태양광 발전 시스템의 대략적인 수량 및 배치, 그리고 태양광 발전 시스템의 대략적인 최대 높이;
2. 공중 참여의 목적은 다음과 같습니다: (i) 제안된 프로젝트의 기술적 측면을 공중에 알리고 이 장의 기준 및 요구사항이 어떻게 충족될 것인지 설명하는 것, (ii) 우려되는 문제를 식별하는 것, (iii) 소통을 촉진하는 것, 및 (iv) 프로젝트로 인해 영향을 받을 수 있는 사람들과 소유자 또는 운영자 간의 대화를 수립하는 것입니다.
3. Announcement of a 30-day comment period in accordance with subsection C D of this section, and the name, telephone number, address, and email address of the applicant who can be contacted by the interested persons to answer questions or to whom comments shall be sent;
4. 이 섹션의 D E항에 따라 개최되는 공개 회의의 날짜, 시간 및 장소에 대한 발표.
5. 규칙 신청에 따른 허가를 지원하기 위해 부서에 제출할 서류의 사본을 열람할 수 있는 장소입니다.
비. C. 소유자 또는 운영자는 제안된 프로젝트 인근의 30-일 의견 수렴 기간 동안 업무 시간 동안 일반인이 접근할 수 있는 장소에 문서 사본을 비치해야 합니다.
C. D. 대중은 제안의 기술적 및 규제적 측면에 대해 의견을 제시할 수 있는 최소 30 일의 시간을 제공받아야 합니다. 의견 제출 기간은 신청자가 처음 지역 신문에 공지를 게재한 후 15 일 이내에 시작해야 합니다.
D. E. The applicant shall hold a public meeting not earlier than 15 days after the beginning of the 30-day public comment period and no later than seven days before the close of the 30-day comment period. The meeting shall be held in the locality or, if the project is located in more than one locality, in a place proximate to the location of the proposed project.
E. F. 이 장의 목적상, 공개 의견 수렴 기간 동안 신청자에게 제안서에 대한 서면 의견을 제출하거나 공개 회의에 서명하고 구두 의견을 제공하는 신청자 및 모든 이해관계자는 이 장의 규칙 및 § 10-1-1197.7 에 따라 허가 절차에 참여한 것으로 간주됩니다. B의 버지니아주 강령.
A. Change of ownership. A permit by rule PBR may be transferred to a new owner or operator if: through an administrative amendment to the permit. The department will incorporate the administrative changes to the PBR after the receipt of the following:
1. The current owner or operator notifies the department at least 30 days in advance of the transfer date by submittal of a notice per subdivision 2 of this subsection Notification of the change in a form acceptable to the department;
2. 통지서에는 기존 소유자 또는 운영자와 신규 소유자 또는 운영자 간에 허가 책임, 적용 범위 및 책임의 이전에 관한 구체적인 날짜를 명시한 서면 합의서가 포함되어야 합니다.
3. 이 조항의 제 2 호에 규정된 계약서에 명시된 날짜에 따라, 허가의 규칙에 따른 이전은 새로운 소유자 또는 운영자에게 효력을 발생합니다.
4. Information required for a change of ownership shall be submitted to the department within 30 days of the transfer date.
5. The department shall not consider the change of operator, ownership, or controlling interest for a project shall not be effective until the department receives notification from both the original applicant and the new applicant.
B. Project modifications. Provided project modifications are in accordance with the requirements of this permit by rule and do not increase the rated capacity of the small solar energy project, the owner or operator of a project authorized under a permit by rule may modify its design or operation or both by furnishing to the department new certificates prepared by a professional engineer, new documentation required under 9VAC15-60-30, and the appropriate fee in accordance with 9VAC15-60-110. The department shall review the received modification submittal in accordance with the provisions of subsection B of 9VAC15-60-30. A PBR name may be changed through an administrative amendment to the permit.
1. 소유권 변경에 필요한 정보는 변경일로부터 10일 이내에 해당 부서에 제출해야 합니다( 30 ).
2. 해당 부서는 통지를 받은 후 해당 부서에서 허용하는 양식으로 PBR에 행정적 변경 사항을 반영합니다.
C. Permit by rule termination. The Modification to an existing PBR, with the exception of administrative changes, shall be in accordance with the provisions of 9VAC15-60-30 B.
1. The applicant shall submit the modification application and include project address, documents, maps, and studies supporting the changes to the existing permit. Information that is unchanged in the existing PBR shall not be submitted. Unchanged information shall be identified and certified as unchanged in the modification application.
2. 이 하위 섹션의 하위 섹션 1 에 요구되는 정보 외에도, 기존 PBR을 변경하려면 9VAC15-60-30 A 2 에 따른 지방 정부의 인증, 9VAC15-60-90 에 따른 공개 의견 기간, 9VAC15-60-110 에 따른 적절한 수수료가 필요합니다.
3. Upon receipt of all required documents and applicable fees, the department shall review the modification submittal in accordance with the provisions of subsection C of 9VAC15-60-30.
D. 기록 보관 및 보고는 다음과 같이 제공되어야 합니다:
1. 소유자 또는 운영자는 다음 마일스톤에 대한 알림을 제공해야 합니다:
a. 해당 날짜로부터 15 일 이내에 프로젝트가 착공된 날짜입니다;
b. 해당 날짜로부터 15 일 이내에 프로젝트가 상업 운영을 시작한 날짜입니다;
c. 해당 날짜로부터 15 일 이내에 프로젝트의 완화 및 회피 계획에 영향을 미칠 수 있는 현장 공사 또는 유지보수가 이루어진 날짜입니다;
d. A map of the project post construction clearly showing panel configuration relative to any required mitigation and incorporates any onsite changes resulting from any onsite construction or maintenance that could impact the project mitigation and avoidance plan within 90 days of completion of such work; and
e. 역사 자원에 대한 완화 조치가 포함된 프로젝트의 경우, 해당 작업 완료 후 90 일 이내에 승인된 완화 조치에 따라 완료된 완화 요건에 대한 시공 후 데모를 제출해야 합니다.
2. 피하거나 완화해야 할 자원이 명확하게 표시된 현장 지도 사본은 공사 중 현장에 보관해야 합니다.
3. 요청이 있는 경우 소유자는 본 PBR에서 보관하도록 요구하는 기록의 사본을 부서에 제공해야 합니다.
4. 통지 후 30 일 이내에 해당 부서에서 요청한 모든 정보를 제공합니다.
E. Pursuant to the Virginia Administrative Process Act (§ 2.2-4000 et seq. of the Code of Virginia), the department may terminate the permit by rule whenever the department finds that the applicant has:
1. The applicant has knowingly Knowingly or willfully misrepresented or failed to disclose a material fact in any report or certification required under this chapter; or
2. After the department has taken enforcement actions pursuant to 9VAC15-60-140, the owner or operator persistently operates the project in significant violation of Failed to comply with the conditions or commitments stated within the permit by rule application; or
3. Violated the project's mitigation plan.
Prior to terminating a permit by rule pursuant to subdivision 1 or 2 of this subsection, the department shall hold an informal fact-finding proceeding pursuant to § 2.2-4019 of the Virginia Administrative Process Act in order to assess whether to continue with termination of the permit by rule or to issue any other appropriate order. If the department determines that it should continue with the termination of the permit by rule, the department shall hold a formal hearing pursuant to § 2.2-4020 of the Virginia Administrative Process Act. Notice of the formal hearing shall be delivered to the owner or operator. Any owner or operator whose permit by rule is terminated by the department shall cease operating his small solar energy project.
A. Purpose. The purpose of this section is to establish schedules and procedures pertaining to the payment and collection of fees from any applicant seeking a new permit by rule Fees shall be collected for an application for a PBR or a modification to an application to modify an existing permit by rule PBR for a small solar energy project subject to Part II (9VAC15-60-30 et seq.) of this chapter. No fee shall be required for administrative permit changes pursuant to subsection A or B of 9VAC15-60-100.
B. 허가 수수료 결제 및 보증금. 규칙에 따른 허가 PBR 신청 또는 변경에 대한 수수료는 신청자가 다음과 같이 납부해야 합니다:
1. Due date. All permit application fees or, modification, or CAPZ mitigation fees if applicable are due on submittal day of the at the time of application or modification package submittal.
2. 결제 방법. 수수료는 가능한 경우 온라인 결제 시스템을 사용하여 징수합니다. 이러한 시스템이 운영될 때까지 수수료는 수표, 환어음 또는 우편환으로 "Virginia주 재무부/DEQ" 으로 수취인을 기재하여 환경품질부, 영수증 관리과로 송부해야 합니다. Box 1104, 버지니아 주 리치몬드 23218.
a. 수수료는 미국 통화로 지불해야 하지만 버지니아 Commonwealth of Virginia주의 기관 및 기관은 수수료 금액에 대해 기관 간 송금을 제출할 수 있습니다.
b. 교육부는 수수료를 전자적으로 납부할 수 있는 수단을 제공할 수 있습니다. 이 부분에 따라 신용카드를 통해 수수료를 전자적으로 징수하는 경우, 해당 결제 처리와 관련된 부서에 비즈니스 거래 비용이 부과될 수 있습니다.
3. 불완전한 결제. 모든 불완전한 결제는 미결제로 간주됩니다.
4. 결제 연체. 부서에서 적절한 대금을 수령할 때까지 PBR 신청 또는 수정 제출은 완료된 것으로 간주되지 않습니다.
a. 연체료에 대한 이자는 버지니아주 법령( 58.1-15 )에 명시된 과소 납부 이자율에 따라 부과될 수 있으며, 해당 정기 이자율에 따라 월 단위로 계산됩니다. 연체된(연체일수 90 초과) 계정에는 10% 연체료가 부과됩니다.
b. 버지니아주 교육부는 연체된 금액을 징수할 때 Virginia주 법에 따라 가능한 모든 구제책을 사용할 수 있습니다.
C. Fee schedules. Each application for a permit by rule PBR and each application for a modification of a permit by rule PBR is a separate action and shall be assessed a separate fee. The amount of the permit application fee is based on the costs associated with the permitting program required by this chapter. The fee schedules are shown in the following table:
1. The fee for a permit application or modification submitted prior to (insert the effective date of the amendments) is identified on Table 1.
표 1
| 
 작업 유형  | 
 수수료  | 
| 
 규칙 적용에 따른 허가 - 정격 용량별: >5 최대 MW 25 >25 최대 MW 50 >50 최대 MW 75 >75 최대 MW 150  | 
 $ 8 , 000 $ 10 , 000 $ 12 , 000 $ 14 , 000  | 
| 
 규칙 수정에 의한 허가 - 이 장의 파트 II에 해당하는 모든 프로젝트의 경우  | 
 $ 4 , 000  | 
2. The fee for a permit application or modification submitted after (insert the effective date of the amendments) is identified on Table 2.
표 2
| 
 작업 유형  | 
 수수료  | 
| 
 NOI fee: >5 최대 MW 20 >20 MW Modification fee for a project subject to Part II of this chapter Incomplete fee: assessed for application review after receipt of an incomplete determination  | 
 $ 2 , 000 $7,500 base fee plus $150 per MW $7,500 base fee plus $165 per MW 20% of original application fee 20% of original application fee  | 
D. Use of fees. All projects that were permitted after (insert the effective date of the amendments) shall be assessed an annual permit maintenance fee. No maintenance fee shall be assessed for projects that were permitted prior to (insert the effective date of the amendments). The annual permit maintenance fee shall be comprised of a base fee of $500 plus $15 per MW of the project. Maintenance fees shall be adjusted annually based on the Consumer Price Index.
1. The annual adjustment of the permit maintenance fees shall be based upon the annual permit maintenance fee amount for the preceding calendar year and the change in the CPI value published by the U.S. Department of Labor for all-urban consumers over the 12-month period ending on August 31 of the calendar year preceding the calendar year in which the permit maintenance fee is assessed.
2. The CPI for all-urban consumers published by the U.S. Department of Labor may be obtained online from the Bureau of Labor Statistics website.
3. No CPI adjustment shall be made for annual permit maintenance fees assessed in the (insert the calendar year the amendments become effective).
4. 연간 허가 유지비 금액은 가장 가까운 정수 달러로 반올림합니다.
5. Within 30 days following the date of the postmark on the bill, the owner shall pay the fee in full by check, draft, or money order made payable to the Treasurer according to subsection B 2 of this section.
E. All applicants, unless otherwise specified by the department, shall submit the following information along with the fee payment in a form acceptable to the department and include the following information:
1. 신청자 이름, 주소, 주간 전화번호;
2. 신청자와 다른 경우 책임자 이름, 주소, 주간 전화번호;
3. 프로젝트 이름과 프로젝트 위치를 입력합니다;
4. Whether the fee is for a new PBR issuance, Incomplete fee, permit maintenance, or permit modification;
5. 제출된 수수료 금액
6. 기존 허가 번호입니다.
F. Fees are assessed for the purpose of defraying the department's costs of administering and enforcing the provisions of this chapter including permit by rule PBR processing, permit by rule PBR modification processing, and inspection and monitoring of small solar energy projects to ensure compliance with this chapter. Fees collected pursuant to this section shall be used for the administrative and enforcement purposes specified in this chapter and in § 10.1-1197.6 E of the Code of Virginia.
E. Fund. G. The fees, received by the department in accordance with this chapter, shall be deposited in the Small Renewable Energy Project Fee Fund as specified in § 10.1-1197.6 F of the Code of Virginia.
F. Periodic review of fees. Beginning July 1, 2013, and periodically thereafter, the H. The department shall will periodically review the schedule of fees established pursuant to this section to ensure that the total fees collected are sufficient to cover 100% of the department's direct costs associated with use of the fees.
A. 이 장에서는 지원자가 부서에 제출할 정보를 수집할 때 사용할 수 있는 리소스에 대해 설명합니다. 이러한 리소스는 인터넷을 통해 사용할 수 있으므로 지원자를 돕기 위해 이 섹션에 나열된 각 참조에 대해 유니폼 리소스 로케이터 또는 인터넷 주소가 제공됩니다.
B. 인터넷에서 사용 가능한 리소스.
1. 버지니아 주 역사적 유적 등록부, 버지니아 주 역사 자원부, 2801 켄싱턴 애비뉴, Richmond, Virginia. 다음 인터넷 주소에서 확인할 수 있습니다: http://www.dhr.virginia.gov/registers/register.htm.
2. 전문 자격 기준, 내무부 장관의 고고학 및 역사 보존을 위한 기준 및 지침(개정 및 주석 포함)(48 FR 44716-740, 2009년 9월 29, 1983), 국립공원 서비스, Washington, D.C. 다음 인터넷 주소에서 확인할 수 있습니다: http://www.nps.gov/history/local-law/arch_stnds_9.htm.
3. The Natural Communities of Virginia, Classification of Ecological Community Groups, Virginia Department of Conservation and Recreation, Division of Natural Heritage, Richmond, Virginia. Available at the following Internet address: http://www.dcr.virginia.gov/natural_heritage/ncintro.shtml.
4. Virginia's Comprehensive Wildlife Conservation Strategy, 2005 (referred to as the Virginia Wildlife Action Plan), Virginia Department of Game and Inland Fisheries Wildlife Resources, 4010 West Broad Street, Richmond 7870 Villa Park Drive, Suite 400, Henrico, Virginia. Available at the following Internet address: http://www.bewildvirginia.org/wildlifeplan/.
5. Pollinator Smart Solar Site Portal, Virginia Department of Conservation and Recreation, Division of Natural Heritage, Richmond, Virginia. Available at the following Internet address: https://www.dcr.virginia.gov/natural-heritage/pollinator-smart.
6. Virginia Pollinator Protection Plan, Virginia Department of Agriculture and Consumer Services, 102 Governor Street, Richmond, Virginia. Available at the following Internet address: https://www.vdacs.virginia.gov/plant-industry-services-pollinator-protection-plan.shtml.
C. 인터넷 애플리케이션.
1. 해안 GEMS 신청서, 2010, 버지니아 주 환경 품질국. 다음 인터넷 주소에서 확인할 수 있습니다: http://www.deq.virginia.gov/coastal/coastalgems.html.
NOTE: This website is maintained by the department. Assistance and information may be obtained by contacting Virginia Coastal Zone Management Program, Virginia Department of Environmental Quality, 1111 East Main Street, Suite 1400, Richmond, Virginia 23219, (804) 698-4000.
2. Virginia Natural Landscape Assessment, Virginia Department of Conservation and Recreation. Available at the following Internet address: for detailed information on ecological cores go to http://www.dcr.virginia.gov/natural_heritage/vclnavnla.shtm. Land maps may be viewed at DCR's Land Conservation Data Explorer Geographic Information System website at http://www.vaconservedlands.org/gis.aspx.
참고: 이 웹사이트는 DCR에서 관리합니다. 실제 셰이프파일과 메타데이터는 DCR 담당자(vaconslands@dcr.virginia.gov) 또는 DCR, 자연유산부, 217 버지니아 주 리치몬드, 주지사 거리 23219, (804) 786-7951 으로 연락하면 무료로 이용할 수 있습니다.
3. Virginia Fish and Wildlife Information Service 2010, Virginia Department of Game and Inland Fisheries Wildlife Resources. Available at the following Internet address: http://www.vafwis.org/fwis/.
참고: 이 웹사이트는 DGIF에서 관리되며, 일반 사용자는 "방문자," 또는 등록된 구독자로서 접근 가능합니다. 그러나 자원별 또는 종별 위치 데이터 및 기록에 접근하려면 등록이 필요합니다. 지원 및 정보는 DGIF(동물 및 야생동물 정보 서비스)에 연락하여 얻을 수 있습니다. 주소: 4010 West Broad Street, Richmond, Virginia 웹사이트: 23230, (804) 367-6913. 
A. Projects meeting one of the following conditions shall be subject to this section:
1. 정격 용량이 1MW 이상 5MW 이하인 프로젝트;
2. Projects with a disturbance zone greater than two acres and less than or equal to 10 acres; or
3. Projects located on previously disturbed or repurposed areas without regard to the rated capacity or size of the disturbance zone and any impact to undisturbed areas is less than or equal to 10 acres.
B. 이 부분에 따라 PBR을 신청하는 신청자는 다음을 제출해야 합니다:
1. The NOI in a form acceptable to the department.
2. A certification by the governing body of the locality wherein the project will be located that the project complies with all applicable land use ordinances.
C. The owner or operator of a small solar energy applicant of a project is not required to submit any notification or certification to the department if he meets at least one of the following criteria:
1. The small solar energy project has either a rated capacity equal to or less than 500 kilowatts one MW or a disturbance zone equal to or less than two acres; or
2. The small solar project falls within at least one of the following categories, without regard to the rated capacity or the disturbance zone of the project:
a. The small solar energy project is mounted on a single-family or duplex private residence.
b. The small solar energy project is mounted on one or more buildings less than 50 years old or, if 50 years of age or older, have been evaluated and determined by DHR within the preceding seven years to be not VLR-eligible.
c. The small solar energy project is mounted over one or more existing parking lots, existing roads, or other previously disturbed areas and any impacts to undisturbed areas do not exceed an additional two acres.
d. The small solar energy project utilizes integrated PV only, provided that the building or structure on which the integrated PV materials are used is less than 50 years old or, if 50 years of age or older, has been evaluated and determined by DHR within the preceding seven years to be not VLR-eligible.
B. 정격 용량이 500 킬로와트 이상 5메가와트 이하이거나 2에이커 이상 10 에이커 이하인 소규모 태양광 에너지 프로젝트의 소유자 또는 운영자는 해당 부서에 통보하고 프로젝트가 위치할 지역 또는 지방의 관리 기관이 해당 프로젝트가 모든 토지 사용 조례를 준수한다는 증명서를 제출해야 합니다.
Solar Permit by Rule (PBR) Notice of Intent (NOI) Part II 9VAC15-60-30 (rev. 2/2020)
Solar Permit by Rule (PBR) Notice of Intent (NOI) Part III 9VAC15-60-130 (rev. 2/2020)
Solar Permit by Rule (PBR) Withdrawal Notice (rev. 2/2020)
Solar Permit by Rule (PBR) Change of Owner/Operator/Name (rev. 2/2020)